• Century Village Reclaimed Water Production Facility

    Project included the demolition of an existing water treatment facility and then construction of a new million gallon prestressed concrete reclaimed water storage tank.

Owner
Palm Beach County WUD
Engineer
Hazen & Sawyer
Contract Amount
$3,598,000
Lost Time Incidents
0
Tank Supplier
Crom Corp.

Project Details

Project included the demolition of an existing water treatment facility and then construction of a new million gallon prestressed concrete reclaimed water storage tank;  reclaimed water pump station; new electrical building, disk filter filtration system; bulk sodium hypochlorite storage tanks and chemical pumping system; polymer feed system; associated instrumentation & electrical upgrades; new landscaping, irrigation, and storm water retention pond.