• Sarasota Venice Gardens WRF Expansion to 3.0 MGD

    This project involved the demolition of the old headworks and construction of a new complete headworks. The crew had zero lost-time incidents on close to 6,000 man hours for the overall project.

Owner
Sarasota County
Design Engineer
MWH
Contract Amount
$4,468,720
Concrete Yardage
704 Yards
Plant Capacity
3 MGD

Project Details

Scope of work for this project involved a new headworks with associated screening and grit removal equipment, anoxic mixers, recycle pumps, return sludge pumps, new blower, electrical building, electrical upgrades and instrumentation. The purpose of the project was to increase the plant capacity from 2.0 million gallons per day to 3.0 million gallons per day to accommodate recent and future expansion.